My inverter is no longer on the CEC approved list. Does that kill the battery rebate?

Not automatically. For an existing VPP-capable hybrid inverter that the battery will use, CER allows a pathway where the inverter was listed when the solar PV system was commissioned — but it must not have been removed because it was declared ineligible or delisted for safety reasons.

Three states to distinguish

Currently listed

For a battery-connected existing hybrid inverter, current listing plus VPP capability can satisfy this part of the pathway, subject to the other program requirements.

Previously listed, no longer current

This can still be viable if it was listed when the PV system was commissioned and was not removed for a safety/ineligibility reason.

Safety-delisted / declared ineligible

That is a different state. CER says an inverter that does not meet the requirements must be replaced with a current approved, VPP-capable inverter for this pathway.